Weekly update w/c 10/09/12

  • Further design work has taken place this week.  The design is proving to be more involved than originally anticipated and additional time will be needed to complete this.  Project Manager to reschedule resources when Resource Manager back from leave next week.
  • Outstanding questions regarding the design are still sitting with Finance, these are being chased up.
  • Initial discussions between the Developer and Dev Tech have taken place, this will allow the technical documentation to be drawn up.