Report for September 2014
- Report Date
- September 2014
Achievements this period
ABS worked with IS Apps resources to create BOXi universe
User acceptance testing completed
Acceptance sign off and delivery achieved.
New budget and milestones agreed by project manager, project sponsor, programme manager and portfolio manager
Issues
- New budget to be approved by WIS
- Acceptance and delivery milestones were missed - remaining milestones must be agreed with project sponsor.
Next Steps
FIS to test purging and archiving of one subledger in LIVE
FIS to complete documentation for FIS users
Deployment sigoff
- Close
The project is RED as new milestones have to be agreed with the project sponsor.
Milestones
| 06-Oct-2014 | Delivery | Deliver |
| 13-Oct-2014 | Deployment Sign off Review | Deliver |
| 20-Oct-2014 | Close | Close |
- Approved budget
- 40.0 days
- Activity this month
- 12.0 days
- Activity this year
- 17.0 days
- Activity to date
- 55.0 days
- Estimate to complete current year
- 17.0 days
- Estimate to complete future years
- 0.0 days