Completion Report

Project Summary:

Project Deliverables

 

All deliverables were achieved

 

1Documented standard operating procedure for purging specified  eFinancials data.MAchieved
2Method to store  purged eFinancials data for later retrieval.MAchieved
3Documented standard operating procedure for archiving purged eFinancials data.MAchieved - done at same time as purge
4Provision of  agreed User Acceptance Test plan.MNot delivered to PM but used by FIS
5Testing of purging and archiving procedures within eFinancials against User Acceptance Test plan.MAchieved
6Implementation of ABS fixes to the  DEV, TEST and LIVE environments as required. MAchieved
7Simple process for querying archived data.HDAchieved
8Proof of concept based on delivered standard operating procedure by archiving one of the ledgers/sub-ledgers in the LIVE environment.MAchieved
9.Document results of purging routine testing,  including any issues reported to ABS.HDAchieved
10.A rollback procedure for immediate reversal of a purge event, to be carried out by IS Applications.MAchieved

 

Success Criteria

 

These success criteria were all achieved:

 

  1. Delivery of a purging and  archiving methodology operating in the live environment which supports the purging of any records from eFinancials without impacting system integrity and which can be used at any pre-planned time to perform record purging..
  2. Purging of records on eFinancials does not affect the operational information needed by the sales or purchase ledgers and information is still summarised in the general ledger
  3. Successful reconciliation of data purged to ensure security of records archived.
  4. The purging of a set of records from eFinancials which proves the process.
  5. A new database  created to allow querying and reporting on archived transactions
  6. Testing of all purging programmes within  the eFinancials  DEV and TEST environment and recording of any issues noted

 

Additional Benefits

 

The team noted the additional benefit that this new functionality had been added without creating an additional system. Maintenance has thus been minimised.

 

  1. The purging and archiving is done via efinancials
  2. The reporting is done via BI

 

Future Developments

 

The archiving facility is planned to be in use for only two years. After this time Finance will be able to confirm the reliability of the ABS purging procedures and there will no longer be a need for archiving purged data.  

 

 

The archiving facility might be improved by  a small enhancement which could be picked up by a future project: 

Analysis of Resource Usage:

Staff Usage Estimate: 63 days

Staff Usage Actual: 71 days

Staff Usage Variance: 13%

Other Resource Estimate: 1 days

Other Resource Actual: 1 days

Other Resource Variance: 0%

Explanation for variance:

Initial Proposal Underestimated 

The initial proposal suggestion  (40 days) was underestimated as the scope and  requirements were not sufficiently understood in order to estimate the effort required to deliver them.  No contingency was allocated. 

The planning and analysis stages took 22 days to complete because  the deliverables were initially unclear and once agreed,  investigations revealed the complexity of the steps required to achieve the deliverables. These had not beenundestood at the proposal stage.  The project was re-estimated at that stage as requiring an additional  21 days to complete with the assistance of the supplier.taking the estimate to 63 days. The project manager  then confirmed the scope with the project sponsor  and additional funding was agreed.

Issues with reconciliation of Purged vs Archived data

The project  team worked with the supplier in order to adapt existing supplier scripts to deliver the full requirements.  The build sign off could not be achieved when expected due to disparities between the data archived (using scripts developed with the supplier) and the data purged (using the existing supplier scripts.  Additional effort was required to resolve these issues and achieve the build review.

Extended duration 

The duration of the project was extended for several reasons:

  • initial business lead retired
  • annual leave of IS Applications staff delayed 
  • annual leave of FIS staff delayed beginning of UAT
  • delay in approving new budget and milestones
  • change in project scope resulted delay to completion of UAT testing
  • delay in agreement of deployment signoff and closure milestones 
  • delay in getting access to BI designer to create BI universe
  • delay in access to BI test to check data ( a licensing issue)

 

Key Learning Points:

Non-standard design and development

 

The team worked with ABS to understand how the existing ABS purging scripts worked, so that the requirements  for archiving the  purged data could be understood, agreed and documented.

The support analyst  then worked with ABS to produce the archiving scripts which were required to be used  in tandem with the existing ABS archiving scripts.

As these procedures were non-standard, the team had to adapt the  usual internal QA procedures but there was less internal  peer review and oversight than  is usual.

In order to gain best value from the ABS resource, the work was sometimes carried out on-site and followed up via email. When on-site the ABS resource split effort between the project and ongoing work for FIS.

The project team consider that working with ABS was successful but recommend that:

  • For similar future work an ABS resource should be booked on-site and dedicated to project work.
  • The ABS resource should be on-site for testing
  • The risk to the budget of working with a consultant  should be assessed and recorded, particularly if the consultant  resource is not dedicated while on-site - for example the risk that the requirements may not be fully understood by the consultant

Outstanding issues:

Internal FIS Documentation

 

IS Applications have provided all documents required for this to be competed by FIS as agreed.

https://www.jira.is.ed.ac.uk/browse/FIN097-9

 

Project Info

Project
Purging and Archiving for eFinancials
Code
FIN097
Programme
Finance (FIN)
Project Manager
Morna Findlay
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
08-Apr-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
20-Oct-2014