Report for September 2014
- Report Date
- September 2014
Achievements in Last Period
- Project Brief signed off
- Patches successfully implemented and tested in eFinancials Development and Test environments
- Build stage of project signed off
- Implementation plan agreed for deploying patches to eFinancials Live environment
Issues
- A couple of issues arose during user testing which have been fully resolved, following consultation with IS Applications and the external supplier ABS
Next Steps
- Project stakeholders to sign off Acceptance stage of project
- Patches to be deployed to eFinancials Live environment
- Project team to sign off Deployment
- Project to be submitted for closure
Target date | Title |
---|---|
17-Oct-2014 | Deployment |
24-Oct-2014 | Completion |
- Approved budget
- 40.0 days
- Activity this month
- 14.9 days
- Activity this year
- 17.6 days
- Activity to date
- 17.6 days
- Estimate to complete current year
- 22.4 days
- Estimate to complete future years
- 0.0 days