Finance BI Improvement: October

Report Date
October 2016

Achievements this period

Review of progress to date on JIRAs transferred from FIN109 & FIN112

  • 3 complete
  • 3 ready for test by business
  • 4 not started

 

Review of other proposed scope items and priority/order.  Preliminary analysis undertaken on the following proposed items to determine if these can be delivered as part of the project:

  • User access to codes restricted to eAuthorisations coding access - Software Dev believe this will be a fairly complex piece of work, and would likely require a small/medium project of it's own - confirmed as out of scope for FIN117.
  • Creation of a BI Dashboard for Finance
  • Universe conversion from UNV to UNX

 

Project brief drafted

  • to be reviewed with stakeholders and signed off

 

Risks

  • The two proposed scope items still to be fully assessed could prove to be too large/complex to deliver as part of this project
  • Specialist BI developer is no longer available, which increases the demand on the remaining development resource, which may in turn delay the outstanding development tasks if there are conflicting priorities for the development team
  • The remaining BI development activity may take longer to complete than initially estimated if not conducted by specialist

Next steps

  • Complete initial analysis and assessment of proposed scope items, and finalise the scope of the project
  • Sign off project brief
  • Confirm development schedule for JIRA items not started and other scope items
  • Agree and publish project milestones
  • Complete business testing of JIRA development

Achieving the above steps should return the project to Green (currently reporting Amber due to unconfirmed scope items).

Project Status
RAG Status
Overall
AMBER
RAG Commentary
Amber status due to outstanding analysis of proposed scope items (to confirm that the project can deliver these items). Path to Green confirmed in 'next steps'.
Change Status
Activity
Approved budget
100.0 days
Activity this month
11.0 days
Activity this year
32.0 days
Activity to date
0.0 days
Estimate to complete current year
32.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Finance BI Improvement
Code
FIN117
Programme
Finance (FIN)
Management Office
ISG PMO
Project Manager
Richard Bailey
Project Sponsor
Lee Hamill
Current Stage
Close
Status
Closed
Start Date
13-Oct-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
04-Aug-2017