Project Status Reports

Title Report Date Time Cost Scope Overall Change
Finance BI Improvement: August 2017 August 2017 BLUE
Finance BI Improvement: July 2017 July 2017 GREEN
Finance BI Improvement: June 2017 June 2017 GREEN
Finance BI Improvement: May 2017 May 2017 GREEN
Finance BI Improvement: April 2017 April 2017 GREEN
Finance BI Improvement: March 2017 March 2017 GREEN
Finance Bi Improvement: February February 2017 GREEN
Finance BI Improvement: January January 2017 AMBER
Finance BI Improvement: December December 2016 GREEN GREEN GREEN GREEN
Finance BI Improvement: November November 2016 AMBER
Finance BI Improvement: October October 2016 AMBER

Project Info

Project
Finance BI Improvement
Code
FIN117
Programme
Finance (FIN)
Management Office
ISG PMO
Project Manager
Richard Bailey
Project Sponsor
Lee Hamill
Current Stage
Close
Status
Closed
Start Date
13-Oct-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
04-Aug-2017

Documentation