Finance BI Improvement: June 2017
- Report Date
- June 2017
Achievements this period
- Finance analysis of BI reports continuing with the target population of reports being analysed
- 'Security Workshop' held on 07/06/2017, Business were educated on creating Persona's to which to map Users requirements and therefore security model to
- It was confirmed with Service Management (Andrew McFarlane) that the hiding of universes could be done under service, rather than project if required
Risks
- Key project resource may be unavailable at critical times due to higher priority work
- The remaining BI development activity may take longer to complete than initially estimated if not conducted by specialist
Next steps
- Business to continue BI report analysis, then begin universe rationalisation analysis (i.e. which universes have no/few reports, and can any remaining reports be either removed or pointed to a newer universe)
- Look to complete the 'Security Review'
- Review JIRA stories
- Approved budget
- 100.0 days
- Activity this month
- 0.8 days
- Activity this year
- 65.2 days
- Activity to date
- 65.2 days
- Estimate to complete current year
- 9.4 days
- Estimate to complete future years
- 14.3 days