Finance Bi Improvement: February
- Report Date
- February 2017
chievements this period
- The issue with reports required for analysis has been overcome. Service Management were able to provide an alternative method to identify the reports that should be targeted for further analysis by the Finance team.
- Finance analysis of BI reports is underway
- JIRA Dev work continues
Risks
- Key project resource may be unavailable at critical times due to higher priority work
- The remaining BI development activity may take longer to complete than initially estimated if not conducted by specialist
Next steps
- Continue BI report analysis
- Hold 'security workshop' once report analysis complete
- Continue development analysis/solutions for JIRAs
- Agree release approach/schedule for JIRAs
- Approved budget
- 100.0 days
- Activity this month
- 9.3 days
- Activity this year
- 66.9 days
- Activity to date
- 66.9 days
- Estimate to complete current year
- 33.0 days
- Estimate to complete future years
- 0.0 days