Finance BI Improvement: April 2017
- Report Date
- April 2017
Achievements this period
- Finance analysis of BI reports is underway with the target population of reports being analysed
Risks
- Key project resource may be unavailable at critical times due to higher priority work
- The remaining BI development activity may take longer to complete than initially estimated if not conducted by specialist
Next steps
- Continue BI report analysis, then begin universe rationalisation analysis (i.e. which universes have no/few reports, and can any remaining reports be either removed or pointed to a newer universe)
- Hold 'security workshop' once report analysis complete
- Approved budget
- 100.0 days
- Activity this month
- 0.3 days
- Activity this year
- 71.7 days
- Activity to date
- 71.7 days
- Estimate to complete current year
- 30.6 days
- Estimate to complete future years
- 0.0 days