Finance BI Improvement: November

Report Date
November 2016
Achievements this period
  • Scope items and priority agreed with stakeholders
  • Project Brief reviewed and signed off
  • Request for Change submitted
  • Project plan drafted, and analysis tasks and durations agreed with Finance
  • Service Management provided BI report to support analysis of universes
Risks
  • Key project resource may be unavailable at critical times due to higher priority work
  • Specialist BI developer is no longer available, which increases the demand on the remaining development resource, which may in turn delay the outstanding development tasks if there are conflicting priorities for the development team
  • The remaining BI development activity may take longer to complete than initially estimated if not conducted by specialist
Next steps
  • Service Management to provide final report to allow Finance analysis to commence ('BI reports unused for 12 months')
  • Confirm development schedule for JIRA items not started and other scope items
  • Finalise plan (incorporating confirmed dev activity from above item)
  • Agree and publish project milestones
  • Submit End of Planning milestone to WIS
  • Begin BI report analysis

 

Project Status
RAG Status
Overall
AMBER
RAG Commentary
Estimates being provided for development items, which will in turn inform the finalised project plan, will return the project to Green.
Change Status
Activity
Approved budget
100.0 days
Activity this month
11.5 days
Activity to date
44.0 days
Estimate to complete current year
56.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Finance BI Improvement
Code
FIN117
Programme
Finance (FIN)
Management Office
ISG PMO
Project Manager
Richard Bailey
Project Sponsor
Lee Hamill
Current Stage
Close
Status
Closed
Start Date
13-Oct-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
04-Aug-2017