Finance BI Improvement: November
- Report Date
- November 2016
Achievements this period
- Scope items and priority agreed with stakeholders
- Project Brief reviewed and signed off
- Request for Change submitted
- Project plan drafted, and analysis tasks and durations agreed with Finance
- Service Management provided BI report to support analysis of universes
Risks
- Key project resource may be unavailable at critical times due to higher priority work
- Specialist BI developer is no longer available, which increases the demand on the remaining development resource, which may in turn delay the outstanding development tasks if there are conflicting priorities for the development team
- The remaining BI development activity may take longer to complete than initially estimated if not conducted by specialist
Next steps
- Service Management to provide final report to allow Finance analysis to commence ('BI reports unused for 12 months')
- Confirm development schedule for JIRA items not started and other scope items
- Finalise plan (incorporating confirmed dev activity from above item)
- Agree and publish project milestones
- Submit End of Planning milestone to WIS
- Begin BI report analysis
- Approved budget
- 100.0 days
- Activity this month
- 11.5 days
- Activity to date
- 44.0 days
- Estimate to complete current year
- 56.0 days
- Estimate to complete future years
- 0.0 days