Finance BI Improvement: January
- Report Date
- January 2017
Achievements this period
- Issue identified with reports required for analysis. Service Management working with BI supplier to resolve. An updated report with new objects has been produced, currently under review by Service Management
- JIRA Dev work underway
Risks
- Key project resource may be unavailable at critical times due to higher priority work
- The remaining BI development activity may take longer to complete than initially estimated if not conducted by specialist
- If the issue with the BI reports which are preventing analysis from fully commencing persists, it may cause subsequent project target dates/milestones to be revised
Issues
- Issue identified with BI reports required for analysis. Service Management working with BI supplier to resolve.
Next steps
- Resolve BI report issues
- Continue BI report analysis
- Hold 'security workshop' once report analysis complete
- Continue development analysis/solutions for JIRAs
- Agree release approach/schedule for JIRAs
- Approved budget
- 100.0 days
- Activity this month
- 8.1 days
- Activity this year
- 56.7 days
- Activity to date
- 56.7 days
- Estimate to complete current year
- 47.3 days
- Estimate to complete future years
- 0.0 days