Finance BI Improvement: March 2017

Report Date
March 2017

Achievements this period

  • Finance analysis of BI reports is underway - target population of reports to be analysed has been identified, and BI users contacted to request that they run any reports they wish to keep by 10 April.  After this date, Finance will re-run the 'unused report' identification process, and begin removing unused reports.
  • 2 JIRAs ready for promotion from DEV environment 

 

Risks

  • Key project resource may be unavailable at critical times due to higher priority work
  • The remaining BI development activity may take longer to complete than initially estimated if not conducted by specialist
  • Risk that a new PM will not be as familiar with the Project

 

Next steps

  • Continue BI report analysis, then begin universe rationalisation analysis (i.e. which universes have no/few reports, and can any remaining reports be either removed or pointed to a newer universe)
  • Hold 'security workshop' once report analysis complete
  • Finance to provide requested information on 2 JIRAs to allow final development (3 JIRAs with outstanding dev activity)
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
100.0 days
Activity this month
3.5 days
Activity this year
70.4 days
Activity to date
70.4 days
Estimate to complete current year
31.9 days
Estimate to complete future years
0.0 days

Project Info

Project
Finance BI Improvement
Code
FIN117
Programme
Finance (FIN)
Management Office
ISG PMO
Project Manager
Richard Bailey
Project Sponsor
Lee Hamill
Current Stage
Close
Status
Closed
Start Date
13-Oct-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
04-Aug-2017

Documentation