Finance BI Improvement: December
- Report Date
- December 2016
Achievements this period
- End of Planning milestone approved by WIS
- Service Management provided final report to allow Finance analysis to commence
- Confirmed development schedule for JIRA items, and ASTA bookings agreed with Resource Manager
- Finalised project plan
- Agreed project milestones
Risks
- Key project resource may be unavailable at critical times due to higher priority work
- The remaining BI development activity may take longer to complete than initially estimated if not conducted by specialist
Next steps
- Begin BI report analysis
- Hold 'security workshop' once report analysis complete
- Development analysis/solutions for JIRAs
- Approved budget
- 100.0 days
- Activity this month
- 4.1 days
- Activity this year
- 0.0 days
- Activity to date
- 48.5 days
- Estimate to complete current year
- 51.5 days
- Estimate to complete future years
- 0.0 days