Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for October 2019 October 2019 BLUE BLUE BLUE BLUE Within Tolerance
Report for September 2019 September 2019 GREEN GREEN GREEN GREEN No Change

Project Info

Project
Corporate Planner Upgrade
Code
FIN133
Programme
Finance (FIN)
Management Office
ISG PMO
Project Manager
Kevin Hone
Project Sponsor
Craig Henderson
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
02-Sep-2019
Planning Date
20-Sep-2019
Delivery Date
17-Oct-2019
Close Date
08-Nov-2019
Overall Priority
Normal
Category
Compliance

Documentation