Organisation

Work/Task Breakdown

 

Planning

  • Project initiation
  • Preparation of brief
  • Project planning
  • Sign-off of brief

Systems Analysis

  • Identify any operating systems, middleware or software that will become obsolete in the next three years
  • Check/update listings of what needs to be addressed/decommissioned
  • Communicate with other programmes to highlight what they need to include in planning
  • Undertake any 'orphan' or problematic migrations and decommissions
  • Pass on details of servers that can be taken out of service to ITI Enterprise
  • Maintain records of all affected servers and systems

Closure

  • Prepare completion report
  • Submit for approval
  • Close project

 

Resources, Skills and Costs

Task Estimate
To identify any operating systems, middleware or software that will become obsolete in the next three years 12 days
Updating registers; communicating with programme managers 8 days
Migrations that are not currently covered by annual plans for 17/18 18 days
Project planning & management/QA 12 days

 

The above estimate is based on last year's project and work carried out in previous years.

Staff from Development Technology and Technology Management will be the main resource (alongside the PM), with involvement from other sections as required. Colleagues from ITI Unix and ITI Architecture will also be involved.

Project Governance

The project sponsor is Stefan Kaempf, and the programme manager is Maurice Franceschi. The business lead is Heather Larnach. This will be the fourth year that this project team will have worked with the PM on this type of project and it is believed that this grouping have a good understanding of what needs to be done and when.

 

Project Stakeholders

Name Business Area Role
Adam Wadee IS Applications, Project Services Portfolio Manager (ISG)
Ana Heyn IS Applications, Production Management Service Support Manager
Anne Finnan IS Applications, Production Management Service Support Manager
Business/Service Owners University of Edinburgh Owners of affected services
David Watters IS Applications, Project Services Project Manager (Project Team Member)
Graeme Wood ITI Enterprise Services Senior Business Lead
Heather Larnach IS Applications, Technology Management Business Lead (Project Team Member)
Mark Lang IS Applications, Development Technology Senior User (Project Team Member)
Martin Campbell ITI Enterprise Services Technical Lead, Unix Infrastructure
Maurice Franceschi IS Applications, Project Services Programme Manager
Muriel Mewissen IS Applications, Project Services Portfolio Manager (Colleges)
Murray Dippie ITI Enterprise Services Technical Lead, Windows Infrastructure
Nikki Stuart IS Applications, Project Services Portfolio Manager (CSG)
Sheila Fraser IS Applications, Project Services Portfolio Manager (USG)
Stefan Kaempf IS Applications, Production Management Project Sponsor (Project Team Member)
Suran Perera IS Applications, Production Management Service Support Manager

 

 

Project Estimations

 See above.

Project Info

Project
Annual Infrastructure Rationalisation Decommissioning 17/18
Code
INF128
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
15-Aug-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
27-Jul-2018
Programme Priority
4
Overall Priority
Normal
Category
Compliance