Migration Instructions

  1. Receive a resource booking for the migration of an application repo to Git.
  2. Andrew Hobden in Production Management will allocate a specific application to migrate.
  3. If additional information is required, such as the path to a repo, please consult with Andrew Hobden and update the Jira with this information.
  4. Complete the application repo migration.
  5. Update the Jira with the broad steps taken, including any issues encountered and their resolution, so that other migrations can benefit from the acquired experience.
  6. Close the Jira.
  7. Inform the PM that the migration is complete; they will update the Migration Decision Tracker, to capture a high-level view of the project's progress.

Repo-Specific Instructions

Git Migration from VSS

Git Migration from SVN

 

Project Info

Project
Migration of VSS and SVN to GIT
Code
INF141
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Nigel Binns
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
29-Oct-2018
Planning Date
30-Nov-2018
Delivery Date
28-Jun-2019
Close Date
12-Jul-2019
Programme Priority
1
Overall Priority
Normal
Category