The Assessment strand of the Student Systems Roadmap

Current project status

Report Date RAG Budget Effort Completed Effort to complete
January 2018 BLUE 368.0 days 366.0 days 0.0

Project Info

Project
Assessment & Progression
Code
SAC057
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Chris Giles
Project Sponsor
Susan Rhind
Current Stage
Close
Status
Closed
Start Date
01-Aug-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
26-Jan-2018
Programme Priority
1
Overall Priority
Higher
Category
Discretionary

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.