Organisation

Work/Task Breakdown and Project Governance

Task

Deliverable

Owner

Project Management

Project authorisation, Planning and Project documents. Communication and coordination with stakeholders. 

Manage project, sign off, resources, budget and reporting.

Project Services

Build It

 Review refresh procedure

 Refresh DUST, DEV, TEST, TRN environments 

 Manage software update

 Scripts and refresh tasks

SSP DEV and IS Devtech

IS Dev Tech

IS Apps Man, SSP BA

SSP DEV

 Test Refresh DUST and  DEV

SSP DEV

 Test Refresh TEST and TRN environments

SSP BA, SS Operations

 Analyse Upgrade, User Stories

SSP DEV and  BA

 Review upgrade procedure

 Upgrade DEV Scripts

SSP BA, Project Services

IS Dev Tech/ SSP DEV

 Manage software updates, Configuration changes

SSP BA, IS Apps Man, Dev Tech, SSP DEV

Migrate Puppet code DEV  Devtech
Upgrade STuTalk to version 2.0  SSP DEV

 Check DEV Upgrade

 SSP DEV

   Automate performence testing scrips for LIVE SSP DEV, IS Apps Man

Check It

 Upgrade TEST -Scripts

IS Dev Tech, SSP DEV, SSP

 Manage software updates, configuration changes

IS Apps Man , Dev Tech, SSP DEV

 Migrate puppet code TEST  Devtech

 Check TEST upgrade- Manage SITS and downstream system communication

SSP BA

 ASOR

Dev Tech, IS Apps Man, SSP BA,

SSP DEV

Document & handover

 Implementation plan

IS Dev Tech, IS Apps Man and SSP DEV/BA

 Update existing TAD and review

IS Dev Tech, IS Tech Man

   Communications to LIVE users SSP Operations

Deploy

 Upgrade TRN

Dev Tech/SSP DEV

Migrate Puppet code TRN Devtech
Upgrade LIVE- Scripts Dev Tech/SSP DEV
Migrate Puppet Code LIVE  

 Manage software updates,  configuration changes

IS Apps Man, Dev Tech

Implement password changes on LIVE  Devtech

 Test LIVE Upgrade

 Manage SITS and downstream system communication

SSP BA

 

 Upgrade DUST  

Dev Tech/SSP DEV

 Refresh TEST from LIVE

DevTech, SSP DEV

Close It

 Closure Review

Project Services, Dev Tech, SSP DEV/BA, IS Apps Man, Student Systems operations

 

Resources Skills and Cost

SSP IS Apps and Project Services days: 220 days

- to be re-estimated after upgrade of DEV environment.

SSP Registry Estimate =120  days (for impact analysis and regression testing for the upgrade )

 

Project Milestones

 

 

 Date  Milestone
16-Oct-2017 Refresh DUST
23-Oct-2017 Refresh DEV
27-Oct-2017 End of Planning
06-Nov-2017 Refresh TEST
13-Nov-2017 REFRESH TRN
17-Nov-2017 Refreshes Complete
17-Nov-2017 Expected release date of 9.5.0
04-Dec-2017 Upgrade DEV
15-Dec-2017 DEV Upgrade complete
08-Jan-2018 Upgrade TEST
02-Feb-2018 Acceptance Sign off
05-Feb-2018 Upgrade TRN
23-Feb-2018 Upgrade LIVE
10-Mar-2018 Fallback date for LIVE Upgrade
29-Mar-2018 Deployment Sign off LIVE Upgrade
09-Apr-2018 Refresh TEST
16-Apr-2018 Clone DUST from LIVE
26-Apr-2018 Close

 

Project Stakeholders 

 

Alison Armstrong Digital Transformation  User  
Brandi Headon Student Systems Senior Support Analyst  
Brenda Kutereba Student Systems Business Analyst  
Defeng Ma IS Development Services Senior Development Analyst  
Douglas Adamson       IS Applications Applications Management Support Analyst  
Ewan Scott IS Development Technology Technical Architect  
Franck Bergeret Service Excellence User (SEP)  
Heather Larnach IS Applications Technology Management Senior Support Analyst  
Iain Fiddes IS Development Services Senior Supplier  
James Thin IS project Services User  ( Exam Timetabling)  
Karen Osterburg Student Systems Partnership Business Lead  
Lisa Dawson Student Systems Project Sponsor  
Luke Manley Student Systems Partnership Testing  
Mark Dobbing IS Development Technology Technical Architect  
Morna Findlay IS Project Services Project Manager and Programme Manager  
Suran Perera IS Applications Management Senior Support Analyst  
Tomasz Pogoda IS Development Services Development Analyst

 

 

Project Info

Project
SITS Double Upgrade
Code
SAC061
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
Brandi Headon
Current Stage
Close
Status
Closed
Start Date
02-Oct-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Programme Priority
1
Overall Priority
Normal
Category
Compliance