Report for September 2019

Report Date
September 2019

Achievements in last period:

  • Supporting adhoc applicant queries.
  • Providing adhoc Scholarship and Funding Recording Support.
  • 10 draft SOPs completed,  6 reviewed and signed off, 4 remain for review and sign-off.

Issues

  • Due to staff being unexpectedly off, there has been a delay to complete the sign off  of the remaining SOP by end Sept. This is now planned for in Oct. We do not expect much impact, as this is off peak period for users

Activities in progress:

  • Providing adhoc Scholarship and Funding Recording Support until handover complete.
  • Completing review and sign-off of remaining SOPs with stakeholders.

 

Milestones

Deliver Annual scholarship set up processing. Handover documentation and SOPs,. Web Guidance 20-Sep-2019
Close Close
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Amber to accomodate SOP handover as reported in the issue
Change Status
Time
Within Tolerance
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
Yes
Escalated to
Programme Manager and Operations
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Student Funding 2 (Implementation)
Code
SAC070
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Andrew Mackenzie
Project Sponsor
Tracey Slaven
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
01-Mar-2018
Planning Date
n/a
Delivery Date
19-Aug-2019
Close Date
09-Sep-2019
Programme Priority
3
Overall Priority
Normal
Category
Discretionary

Documentation