Closure Report

Project Summary

This project was set up to implement  a new subject coding system - the Higher Education Classification of Subjects (HECoS) - as a replacememnt for the Joint Academic Coding System(JACS)  currently used for the HESA statutory returns. 

This project had 2 objectives, both fully delivered:

Objectives

Deliverables

Benefits

Success Criteria

Priority   

Delivered?  

O1-Complete conversion to HECoS

D1-Agree recoding structure for programme and subject codes

D2-Convert all JACS codes in the student record incl programmes with missing codes

Support the production of the return

Valid codes for use across student systems

  • Deadline is met for the next statutory return. Student Data team needs the new code to start validating the data from Feb to meet their deadline
  • The subject codes are correct and can be used by GaSP and the Student Data team

MUST

 

D1- Yes

D2- Yes**

O2-Update processes, reports and downstream feeds where JACS codes are currently used

Implement system changes

D3-in the student record,

D4- in the reporting BI universes,

D5 -in the downstream feeds and

D6 - in the ‘IS programme’ used to produce the current statutory return

Support the production of the HESA return

Service continuity once conversion made

  • Deadline is met for the next statutory return
  • No impact to BAU service: no bugs are reported post live

 

MUST

 D3- Yes

D4- Yes

D5- Yes

D6- Yes

**in the end we only converted JACS codes to HECoS codes on programmes that were still active in 2019/0, and JACS codes have been retained on historic programmes. This does not impact any areas of business adversely though.

Analysis of Resource Usage:

Staff Usage Estimate: 90 days (IS Apps: Developer, PM, Apps Man, Dev Tech)

Staff Usage Actual: 52 days

Other Resource Estimate:  BA and tester from SSP not estimated at planning

Other Resource Actual: BA and tester from SSP: 66 days

Other Resource noted but not recorded: Effort from student systems Student Analytics and Insights team (business lead and resource to help with the code conversion and BI testing)

 

The go live milestone  was achieved on 14th May. The delay from the original plan ( was 5th Feb) is explained by a number of reasons:

  • Dev resource availability as a result of two industrial actions,
  • PM conflicted on P&M work,
  • Dependency on the SITS upgrade to be completed as a pre-requisite. The upgrade  was delayed to 28 Apr (was 8 Mar ) 
  • Dependency- Delay in getting a software update from Tribal the vendor, pre-required to implement some of the changes

Outcome Key Learning Points

What went well
  • Collaborative effort across several teams from SSP, IS Apps and Cucciculum Return/BI team, especially as new ways of working were being implemented as a result of Covid19. Excellent co-operation amongst resources involved in the testing and any subsequent changes.
  • Communication on Teams
  • Management of the external dependencies

What did not go so well

  • Timescales changed due to higher priority projects needing the BA.  It caused more work in the end as the Business and SSP side had to keep thinking their way back into what had already been done.  However we did deliver on time.
  • It  wasn’t just a conversion of codes, but also a recoding exercise. As there was conflict in securing Subject Matter Expert's time during analysis and preparation of the import files, this resulted in re-working of some of the data and subsequent re-checking of files. Data was converted in the Test environment in January, but further testing carried out in the few weeks prior to Live implementation resulted in last minute data changes.

Lessons learned

n/a

Outstanding Issues

They will be addressed by the Curriculum Return team in student systems:

-There a few data issues regarding incorrect cost centers identified during the returns being run in the HESA 'kit'

-For deliverables 4 (BIS universes) & 6 (IS program): I've raised Unidesk I200616-0256 to investigate compatibility errors that have appeared in one key BIS report since implementation. While we've still to identify the cause of the report error there's a good chance it's related to the data model changes we made.

 

Project Info

Project
Implementation to HECoS codes
Code
SAC082
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Franck Bergeret
Project Sponsor
Paula Webster
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
23-Sep-2019
Planning Date
28-Oct-2019
Delivery Date
30-Apr-2020
Close Date
19-Jun-2020
Programme Priority
1
Overall Priority
Normal
Category
Compliance

Documentation

Close