Report for August 2025
- Report Date
- August 2025
Achievements in Last Period
- The final release for this Project, R2: API for updating the PG Degree Finder for CAM, replacing manual feed, was successfully released to Live on the 25th August 2025
- Deployment checklist reviewed with IS Apps Production
- The remaining open Jira were reviewed with the Project Team with actions taken to close those that remained, no concerns or issues were raised
- The **DRAFT Closure Report was reviewed with the Project Team, updated and circulated ahead of Closure
- New Project Manager assigned and coming up to speed with the Project
Issues and Risks
- None
Next Steps
- Complete Handover to Operations and IS Apps Production
- Gain agreement to and close the Project
Future Milestones
| Stage | Milestone | Due Date |
| Deliver | Review DSOR incl documentation | 15-May-2025 |
| Close | Close (major) | 30-May-2025 |
#Please note that both of the Milestones above have slipped but are in the process of being updated / closed as part of Project Closure works.
- Approved budget
- 382.0 days
- Activity this month
- 12.4 days
- Activity this year
- 12.4 days
- Activity to date
- 446.4 days
- Estimate to complete current year
- 2.5 days
- Estimate to complete future years
- 0.0 days