Report for August 2025

Report Date
August 2025
 

Achievements in Last Period

  • The final release for this Project, R2: API for updating the PG Degree Finder for CAM, replacing manual feed, was successfully released to Live on the 25th August 2025
  • Deployment checklist reviewed with IS Apps Production
  • The remaining open Jira were reviewed with the Project Team with actions taken to close those that remained, no concerns or issues were raised 
  • The **DRAFT Closure Report was reviewed with the Project Team, updated and circulated ahead of Closure
  • New Project Manager assigned and coming up to speed with the Project

 

Issues and Risks

  • None

 

Next Steps

  • Complete Handover to Operations and IS Apps Production
  • Gain agreement to and close the Project

 

Future Milestones

Stage Milestone Due Date
Deliver Review DSOR incl documentation 15-May-2025
Close Close (major) 30-May-2025

#Please note that both of the Milestones above have slipped but are in the process of being updated / closed as part of Project Closure works.

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Issue - Delay in issuing closure report Impact - Closure date is now out of tolerance Mitigation - Update Closure date through Apps Review and close the Project
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
382.0 days
Activity this month
12.4 days
Activity this year
12.4 days
Activity to date
446.4 days
Estimate to complete current year
2.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Delivering Student Records API
Code
SAC106
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Richard Bailey
Project Sponsor
Lizzie Beattie
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
10-Jun-2024
Planning Date
28-Aug-2024
Delivery Date
05-May-2025
Close Date
12-Sep-2025
Overall Priority
Normal
Category
Discretionary