- Report Date
- September 2025
Achievements in Last Period
- Handover to Operations and IS Apps Production completed
- Agreement reached to close the Project, which was noted at Application Review 11-Sep-2025
- Project closed
Issues and Risks
Next Steps
Future Milestones
| Stage |
Milestone |
Due Date |
| Close |
Close (major) |
12-Sep-2025 - CLOSED |
- Approved budget
- 382.0 days
- Activity this month
- 6.2 days
- Activity this year
- 18.9 days
- Activity to date
- 452.9 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days