Report for August 2025
- Report Date
- August 2025
Achievements in Last Period
-
Release 3 for the HESA DR Process,which added an additional field to one of the forms in the application, was deployed to LIVE 25-Aug-2025, this is expected to be the final release required for the 24/25 Return.
- New Project Manager assigned
Issues
-
None
Next Steps
- Establish:
- With Release 3, as noted above, that Delivery - Major milestone has been achieved
- Next steps and continue to monitor if anything is still required for the 24/25 Return (nothing is expected)
- Engage with Sponsor, Programme Manger and Key Project Stakeholders to agree 24/25 Return Project Closure / ascertain what is required for the 25/26 Return
Future Milestones
#Please note that milestones below need to be established and agreed as part of Planning:
| Stage | Milestone | Due Date |
| Deliver | Delivery - Major | 31-Jul-2025 |
| Close | Closure - Major | 26-Sep-2025 |
- Approved budget
- 50.0 days
- Activity this month
- 6.6 days
- Activity this year
- 6.6 days
- Activity to date
- 64.6 days
- Estimate to complete current year
- 15.0 days
- Estimate to complete future years
- 0.0 days