Report for August 2025

Report Date
August 2025

Achievements in Last Period

  • Release 3 for the HESA DR Process,which added an additional field to one of the forms in the application, was deployed to LIVE 25-Aug-2025, this is expected to be the final release required for the 24/25 Return.

  • New Project Manager assigned

 

Issues 

  • None

 

Next Steps​

  • Establish:
    • With Release 3, as noted above, that Delivery - Major milestone has been achieved
    • Next steps and continue to monitor if anything is still required for the 24/25 Return (nothing is expected)
    • Engage with Sponsor, Programme Manger and Key Project Stakeholders to agree 24/25 Return Project Closure / ascertain what is required for the 25/26 Return

 

Future Milestones

#Please note that milestones below need to be established and agreed as part of Planning:

Stage Milestone Due Date
Deliver Delivery - Major 31-Jul-2025
Close Closure - Major 26-Sep-2025

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
50.0 days
Activity this month
6.6 days
Activity this year
6.6 days
Activity to date
64.6 days
Estimate to complete current year
15.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Data Futures - Support 24/25 Return
Code
SAC111
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Richard Bailey
Project Sponsor
Lisa Dawson
Current Stage
Deliver
Status
In Progress
Project Classification
Run
Start Date
14-Apr-2025
Planning Date
15-May-2025
Delivery Date
24-Oct-2025
Close Date
31-Oct-2025
Overall Priority
Normal
Category
Compliance

Documentation