AP45-019

 

It is a compliance project to support the annual statutory HESA return. 

New requirements are expected which will require analysis and configuration changes in EUCLID to meet the hard deadlines

Current project status

Report Date RAG Budget Effort Completed Effort to complete
September 2025 GREEN 97.0 days 77.6 days 10.0

Project Info

Project
Data Futures - Support 24/25 Return
Code
SAC111
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Richard Bailey
Project Sponsor
Lisa Dawson
Current Stage
Deliver
Status
In Progress
Project Classification
Run
Start Date
14-Apr-2025
Planning Date
15-May-2025
Delivery Date
24-Oct-2025
Close Date
31-Oct-2025
Overall Priority
Normal
Category
Compliance

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.