Impact
Priority and Funding
This is a priority 2 core funded project. The estimate is 74d in total, of which 24d is in 16/17 and 50d continuing into 17/18.
Impact and Dependencies
The impact of this project is expected to be changes to the UG and PG applications.
Project Risks
1 | Higher priority projects take precedence, impacting timelines | Medium | High | AMBER | Open | Paul McNulty | |
2 | Annual leave may impact budgets and timescales | Medium | Medium | AMBER | Open | Chris Konczak | |
3 | Systems may be switched off if there is a hack | Critical | Medium | AMBER | Open | Stefan Kaempf | |
4 | Quick fixes will be undertaken to meet legal requirements and need rework to enable php5.3.3 migration | Low | High | AMBER | Open | Niall Bradley | |
5 | Risk that a PHP upgrade may be required | Medium | Low | GREEN | Open | Mark Lang | 14-Jun-2017 |
7 | Estimate is higher than budget allocation | Medium | Critical | AMBER | Open | Niall Bradley | 14-Jun-2017 |