Organisation

Work/Task Breakdown

Request for change has been raised: C1706-048

Planning Project Management  Project Services
  Programme Management Project Services
  Quality Assurance & Resourcing Directors Office
  Familiarisation Software Development
  PG & UG Estimates Software Development
  Weekly team meetings for PG & UG (assume 0.5h for design, build and test phases) All teams
     
Business Analysis  Business Analysis & Completion of Business Requirements Document (BRD) & draft UAT plan CAM
  Communications Strategy CAM
     
Systems Design Technical Architecture Document (TAD) Updates Development Technology
  Design Review

Development Technology

Technology Management

     
Build JIRA 1 - Change display logic for Fees information on programme template (PG) Software Development
  JIRA 2 - Update all instances of "Key Information Set" text in UG admin and UG degree finder Software Development
  JIRA 3 - Ability to overwrite cascading subject content with programme content Software Development
  JIRA 4 - Introduce DPT links to programme records (PG) Software Development
  JIRA 5 - Ability to publish multiple instances of the undergraduate degree finder Software Development
  Peer Testing Applications Management
  Build Review All teams
     
Integration  Deploy to TEST Development Technology
  Integration Testing & support for re-work Applications Management
  Integration Re-work Software Development
  Integration Review All teams
     
Acceptance Communications Actions CAM
  UAT CAM
  Support for UAT & complete any fixes Software Development
  Support for UAT & complete any fixes Applications Management
  Deployment Checklist Applications Management
  Deployment Checklist Technology Management
  Acceptance Review All teams
     
Deployment Check LIVE Deployment CAM
  Deploy to LIVE Software Development
  Post Deployment Support - pre closure Applications Management
  Deployment Review All teams
     
Closure Closure All teams

 

Resources, Skills and Costs

Project Services: 22 days

Software Development: 38 days

Development Technology: 3 days

Applications Management: 8 days

Technology Management: 1 day

Director's Office: 1 day

 

Project Stakeholders

Communication Plan  
Adrian Richardson IS Apps Software Developer
Ailsa Vamplew Communications & Marketing Senior User & Acting Project Sponsor UG
Brian Denholm Applications Management Production Management Coordinator (for Applications Management)
Chris Konczak Project Services Project Manager
Geir Granum IS Apps Senior Software Developer
Heather Larnach Technology Management Technology Management
Jim McGeorge USG / STU USG Portfolio Owner and STU Programme Owner
Karen Osterbrug Student Systems Head Business Process Enhancement
Mark Lang Development Technology Development Technology Team Manager
Niall Bradley Communications and Marketing Project Sponsor
Paul McNulty IS Apps Development Resource Manager
Sheila Fraser Project Services Programme Manager
Steven Ross Communications and Marketing Senior User & Acting Project Sponsor PG
Suran Perera Applications Management Support for Production Co-ordinator

Project Estimations

 

 

AttachmentSize
Office spreadsheet icon Three point estimate120 KB

Project Info

Project
CAM  Degree Finders - Compliance with Legislation & Guidance
Code
STU256
Programme
Student Services (STU)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Niall Bradley
Current Stage
Close
Status
Closed
Start Date
01-May-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Jun-2018
Programme Priority
1
Overall Priority
Higher
Category
Compliance