Organisation

Work/Task Breakdown

  1. Stage

     

    Task

    Who

    Resource cost

    Planning

     

    1. Project Brief and Plan
    2. Set up wiki page
    3. Signoff
    1. PM - Sue
    2. LTW-Myles
    3. All
    1. 2d
    2. LTW
    3. in QA cost

    Build

    Learn Upgrade

     

    1. Upgrade to latest version of Java in Dev
    2. Set up environments
    3. Peer testing
    4. Document and complete test documentation and implementation plan
    5. Support from Chris
    1. Dev
    2. DevTech
    3. DevTech
    4. DevTech
    5. TechMan
    1. 1d
    2. 2d
    3. 0.5d
    4. 0.5d
    5. 1d

    Build

    Building Blocks x 5

    1. Prioritise Building blocks for development purposes
    2. Update Spring within building blocks
    3. Compile them to the latest Learn libraries
    4. Peer testing
    5. Document and complete test documentation

    Dev

    3d per BB

    Build

     

    Update TAD-minor updates

    DevTech

    0.5d

    Integration

     

    1. Deploy to Test
    2. Integrate with external suppliers, data feeds, MyEd and timetabling
    3. Testing
    4. Rework
    5. Security scan
    6. Signoff
    7. Support from Chris
    1. DevTech
    2. DevTech
    3. AppsMan
    4. Dev /DevTech
    5. TechMan
    6. All
    7. TechMan
    1. 1d
    2. 1d
    3. 2d
    4. 1d
    5. 0.5d
    6. in QA cost
    1. 1d

    Acceptance

     

    1. Deployment Checklists APPS
    2. Deployment Checklists TECHMAN
    3. UAT -All Learn feeds (Course and user) tested and working on test
    4. Rework
    5. Signoff
    1. AppsMan
    2. TechMan
    3. LTW
    4. Dev /DevTech
    5. All
    1. 0.5d
    2. 0.5d
    3. LTW
    4. 1d
    5. in QA cost

    Deploy

     

    1. Deploy Upgrade and Building blocks to Live
    2. All Learn feeds (Course and user) tested and working on  live
    3. Security scan
    4. Post Deployment Support
    1. DevTech
    2. LTW
    3. TechMan
    4. Dev /DevTech
    1. 1d
    2. LTW
    3. 0.5d
    4. 0.5d each

    Closure

     

    1. Closure review

    Sue + all contributing

    1.5d

 

Resources, Skills and Costs

This project has been estimated at 71 days IS Apps time (57d best case).

  • Project Services 19 days
  • ISG Development 19 days
  • DevTech - 14 days
  • Production Management -9 days

Not included: resource management, unplanned, meetings and QA

Note that the time for LTW staff or IS Apps Service Management is not included in the project estimate.

 

 

Project Governance

This project will be governed by the standard IS Applications project procedures.

 

Project Stakeholders

 

 

AttachmentSize
Image icon stakeholders.png30.81 KB

Project Info

Project
Learn Upgrade
Code
TEL043
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Anne Mathison
Project Sponsor
Josephine Kinsley
Current Stage
Close
Status
Closed
Start Date
07-Nov-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
18-Aug-2017
Overall Priority
Higher
Category
Compliance