Overview
Background
At present the LEARN system operates via an Oracle database. Currently the version we are operating on is several levels behind the newest version. This has led to the system being under extended support from Oracle, but at a cost. Extended support will become unavailable in 2018.
Currently at 11.2.03 the plan is to upgrade to 12.2 otherwise known as 12c. This is the strategic direction for all Oracle platforms and to keep support rationalised.
Scope
This project is limited to the Oracle version upgrade only.
Upgrades to other supported software needed for the database upgrade will be considered, and where required, tested and installed to ensure a succesful Oracle upgrade
Out of scope
- Any upgrades to LEARN other than those mentioned above
- Changes to Upstream / Downstream systems
Objectives
Bring LEARN Oracle database up to 12c software level so as to ensure compliance and Oracle support.
Deliverables
|
NR |
Objectives / Deliverables |
Success Criteria |
Priority |
|
|
|
|
|
|
|
|
O1 |
Upgrade to new version of Oracle database on non-LIVE systems |
|
|
|
|
D1 |
Upgrade DEV/TEST to Oracle 12c |
Version 12c installed and working with LEARN as specified
|
Must |
|
|
O2 |
Move LIVE to Oracle 12c environment |
LIVE Oracle 12c supporting LEARN system |
|
|
|
O3 |
Manage communications with stakeholders |
|
|
|
|
D2 |
Produce a viable communications plan |
Produce a viable communications plan. |
Must |
|
|
D3 |
Delivery of a communications plan to stakeholders |
Stakeholders engaged in line with plan |
Must |
|
|
|
||||
| O3 | Leverage Benefits of supported system | Oracle database captured within the support agreement | ||
| 04 | Test Integration Systems | Integration works as specified | ||
| D4 | Ensure MyEd Channel works | Must | ||
| D5 | Ensure Eugex / IDM data feeds work correctly (not in DEV) | Must | ||
| D6 | Ensure Native, 3rd Party and custom Building Block and integrations work | Must | ||
| D7 | Ensure the LTW Helpdesk tool works | Must | ||
| D8 | TELSMI Reporting works | Must |
Benefits
Support costs reduced
More reliable platform
Success Criteria
- Identification of benefits, risks and costs
- Delivery of Communications
- Delivery of agreed recommendation
- Upgrade Oracle to 12g
- Move to Oracle 12g systems environment
- BI reporting still working as specified
- LEARN system functioning as designed
- Integration works correctly
Project Milestones
| Target Date |
Previous Date | Title | Stage | Complete |
|---|---|---|---|---|
| 27-Nov-2017 | 13-Nov-2017 | Planning Review | Plan | Yes |
| 09-Feb-2018 | No date available | Build Review | Build | No |
| 14-Feb-2018 | No date available | Integration Review | Integrate | No |
| 28-Feb-2018 | No date available | Acceptance Review | Accept | No |
| 10-Mar-2018 | No date available | Deliver | Deliver | No |
| 23-Mar-2018 | No date available | Deployment Review | Deliver | No |
| 03-Apr-2018 | No date available | Closure Review | Close | No |