Report for November 2019
- Report Date
- November 2019
Achievements in Last Period
- Decommissioning of legacy QMP platform now to take place in 2020 (removed from scope of this project).
- Latest updated TAD now handed over to Production Management.
- It was requested that DR testing be carried out before project closure however the outcome of discussion with ITI was proposal to move on to the stretch cluster, given that DR has been verified on the platform.
- Closure milestone date moved to 20/12/19.
Issues
- No major issues but an outstanding action preventing project closure (migration of VMs to stretched cluster) which has been impacted by UCU industrial action and as a result a PICCL has been added to push the closure out.
Next Steps
- Ensure platform is on infrastructure with verified level of DR.
- complete project closure.
Milestones
|
20-Dec-2019 |
Rag commentary: Project is AMBER
Overall RAG being flagged as AMBER as there is an open issue preventing closure.
- Approved budget
- 119.0 days
- Activity this month
- 1.4 days
- Activity this year
- 7.3 days
- Activity to date
- 140.3 days
- Estimate to complete current year
- 6.6 days
- Estimate to complete future years
- 0.0 days