Report for January 2020
- Report Date
- January 2020
Achievements in Last Period
- Change request for migration of LIVE platform to the metrostretch cluster submitted to Go CAB (and approved after clarification).
- Project team agreed to move closure milestone date to 21/02/20 to allow this work to be completed and review closure report.
- LIVE platform successfully migrated to the Metrostretch cluster.
Issues
- No major issues. All outstanding tasks now complete and project can be closed.
Next Steps
- complete project closure.
Milestones
|
21-Feb-2020 |
Rag commentary: Project is AMBER
Overall RAG being flagged as AMBER as closure milestone moved out.
- Approved budget
- 119.0 days
- Activity this month
- 1.3 days
- Activity this year
- 12.3 days
- Activity to date
- 145.3 days
- Estimate to complete current year
- 0.1 days
- Estimate to complete future years
- 0.0 days