Priority and Funding

This project is priority 2. It is core funded, with budget of 10d confirmed initially. Contingency is being held at the programme level in 16/17 should this increase (see risks).

Impact and Dependencies

This is a stand-alone system, there are no dependencies. There is a potential impact (see risk 3) if just upgrading the apache tomcat does not work, as it would take additional Project Manager and Software Development time that is not currently in the plan.

Project Risks

1 The DEV environment is not suitable for project work Medium High AMBER Open Sheila Fraser 20-Apr-2017

view

2 The TEST environment is not suitable for testing Medium High AMBER Open Sheila Fraser 20-Apr-2017

view

3 The approach of just upgrading the apache tomcat software version does not work and so the application would require substantial rework High Medium AMBER Open Stefan Kaempf 20-Apr-2017

view

4 Holidays or unexpected business priorites impact the schedule Medium Medium AMBER Open Sheila Fraser 20-Apr-2017

view

5 Edinburgh Global are not sufficiently confident in developing test scripts Low Medium GREEN Open Dorothy Watson 20-Apr-2017

view

6 The apache tomcat updates are not stand-alone, i.e. the server needs further updates, potentially impacting other applications Medium Low GREEN Open Stefan Kaempf 20-Apr-2017

view

7 Unforseen absence Low Medium GREEN Open Sheila Fraser 20-Apr-2017

view

Project Info

Project
Edinburgh Global Directory End of Life Compliance
Code
USG004
Programme
USG Portfolio Projects (OTHUSG)
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
14-Apr-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
14-Jul-2017
Programme Priority
1
Overall Priority
Normal
Category
Compliance