Report for December 2020
- Report Date
- December 2020
Achievements this period
- Estimation completed
- Brief written and distributed
- Resourcing assigned
Issues
- Delay in planning sign off due to workload in Project Services during December has resulted in an Amber RAG status of the project. The project team have had a project brief review with some amendments to make to the milestones and consequently the resourcing. Aim to getting the brief into WIS for Friday 22/01/2021
Next Steps
- Milestone amendments
- Brief Signoff
- Analysis work to commence
- Open JDK upgrade to commence
Milestones
Planning | 22-Jan-2021 |
Open JDK Upgrade - DEV | 12-Feb-2021 |
Open JDK Integration complete | 19-Feb-2021 |
MyEd Navigation Fix | 19-Feb-2021 |
Assessment complete for uPortal, Containers, Notifications, React, User and Staff interface | 26-Feb-2021 |
Open JDK UAT Compete | 26-Feb-2021 |
MyEd navigation fix from wps004 UAT complete | 26-Feb-2021 |
Open JDK Deploy to LIVE | 02-Mar-2021 |
- Approved budget
- 0.0 days
- Activity this month
- 2.5 days
- Activity this year
- 7.0 days
- Activity to date
- 7.0 days
- Estimate to complete current year
- 100.0 days
- Estimate to complete future years
- 0.0 days