Report for September 2012

Report Date
September 2012

Achievements in Last Period

  • Planning complete and brief signed off
  • Configure Server and install core Drupal modules

Issues

  • No issues to report at this stage

Next Steps

  • Prioritisation of requirements
  • Infrastructure configuration
  • Module selection

Milestones

Target dateTitle
22-Aug-2012Initiate Project
03-Oct-2012Stage 1 - Planning
19-Nov-2012Stage 2 - Build and Evalute
26-Nov-2012Stage 3 - Report to UWS Governance Group
21-Dec-2012Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
100.0 days
Activity this month
16.2 days
Activity this year
24.2 days
Activity to date
24.2 days
Estimate to complete current year
75.8 days
Estimate to complete future years
0.0 days

Project Info

Project
Drupal Proof of Concept Evaluation
Code
UWS006
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
17-Aug-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Dec-2012
Programme Priority
1
Overall Priority
Normal

Documentation

Not available.