Report for September 2012
- Report Date
- September 2012
Achievements in Last Period
- Planning complete and brief signed off
- Configure Server and install core Drupal modules
Issues
- No issues to report at this stage
Next Steps
- Prioritisation of requirements
- Infrastructure configuration
- Module selection
Milestones
| Target date | Title |
|---|---|
| 22-Aug-2012 | Initiate Project |
| 03-Oct-2012 | Stage 1 - Planning |
| 19-Nov-2012 | Stage 2 - Build and Evalute |
| 26-Nov-2012 | Stage 3 - Report to UWS Governance Group |
| 21-Dec-2012 | Closure |
- Approved budget
- 100.0 days
- Activity this month
- 16.2 days
- Activity this year
- 24.2 days
- Activity to date
- 24.2 days
- Estimate to complete current year
- 75.8 days
- Estimate to complete future years
- 0.0 days