Report for August 2025

Report Date
September 2025

SSP Programme Report - August 2025  for Lisa Dawson (Academic Registrar)

Section one: programme summary, risks and forward look and resource update

Section  two: projects in progress with status amber or red

Section three: projects not started

Section four: closed or withdrawn projects

The format of this programme reporting is reporting by exception: each of the projects which are GREEN, i.e. on track to deliver the agreed scope within the agreed milestones and agreed budget are not reported in Section Three. For GREEN projects the recent achievements and next steps can be found from selecting the project on the SSP Programme Home Page and viewing the relevant monthly report (listed on the right hand side of the project view).

 The RAG will reflect the changes over the last month as per IS guidance LINK

Section One: Programme Summary 

RAG status:  the programme is AMBER

  • 1 Project reporting RED
    • SAC112 - BI Suite - Due to resource challenges
  • 3 Projects are reporting AMBER
    • SAC105 - Due to stories outstanding and closure milestone missed
    • SAC106 - Due to a delay in closure
    • SAC109 - Due to funding not being confirmed for 25/26 yet
  • There is a current gap in Programme Manager resource which is being covered however we are looking at resolving this challenge asap
  • Programme Planning took place and a baseline plan will be shared for review/sign off in the coming weeks
  • Path replacement and enhancement (SAC110): Suspended due to ongoing BA resource issue. Senior BA moved on to Teaching Timetabling & Course Selection until the end of July. Project will pick up again in August
  • SSP is  continuing to support the Strategic Change projects approved by UIPB starting with (1) Curriculum Transformation project (REGCT01): developing PGT requirements for business case and challenge course framework, and(2) Teaching Timetabling/Course Selection.

Red and Amber Programme Risks & Issues

Risks are being monitored fortnightly with programme owner and the SSP management team, and recorded in the Risk Register LINK

EUGEX refresh take longer impacting users Amber Lizzie Beattie
Single point of failures for key services Amber    Lizzie Beattie
Conflicting governance for SSP programme Amber Lisa Dawson
PATH end of life summer 2026 Amber Lizzie Beattie
Impact of Strikes Amber Lisa Dawson

 

Section Two: Projects in Progress with status of Red or Amber

To see Green projects, select the project on the SSP Programme Home Page and view the relevant monthly report (listed on the right hand side of the project view).

Project  Issue or change resulting in AMBER or RED Status

Tuition Fee Improvements

PM Alexandra Mezeul

Amber

Issue (or risk): only 24/25 funding has been confirmed and is secured; the remaining 25/26 and 26/26 funding has been escalated to the Portfolio Manager and Portfolio Owner to secure with senior leaders in ISG. The Risk and Issue have been logged. Currently, the project team can continue its momentum as the PM, Owner, and Sponsor monitor and control the issue. Once funding is secured, we will be able to continue into future years without constraint on budget. If we are unable to secure the remaining necessary funds, then we will be forced to re-scope the project to fit the allocated budget.

Next steps is for the PM and Portfolio Manager to present the funding case for the project to budget holders at the end of June and request the money be ear-marked for the project due the benefits expected to be delivered. The project team will also review the sequencing of deliverables to make sure everyone is happy with our executed work given full funding may not be secured.

Link to status report - August RAG Status Report | Project Management

BI Suite/EUCLID reporting Discovery

PM Ailsa Glass

Red

Issue - SSP do not have Senior BA resource to allocate to the project. The Reporting Manager in the SAIM Team does not have capacity for this work . Impact - The Senior BA and Reporting Manager are the key resources to progress with analysis and the user engagement /planned workshops to understand use of BI for students and Programme data across the university and what options we may have to deliver reporting if we were to decommission BI Suite Action: Funding from ISG to be discussed. Potentially delay project to 25/26

Link to status report -  Report for August 2025 | Project Management

Delivering Student Records API 

PM Richard Bailey

Amber

Issue - The project is now outwith tolerance for closure

Next Steps - New PM assigned to take the project to closure

Link to status report - Report for August 2025 | Project Management

ESC

PM Richard Bailey

Amber

Issue - Stories still outstanding and project is beyond the closure milestone

Next Steps - Project is being replanned and implementations will be scheduled following the September change freeze

Link to status report - Report for August 2025 | Project Management

Section Three: Projects Not Started

Project Info Programme Manager's Commentary
Curriculum Management 

 The business case  was not approved to start yet by UIPB in Dec 24, due to level of change and costs,  more work is required for resubmission in 25/26 

 

CSI work prioritised

The School bulk upload for course enrolments was withdrawn after benefit/cost evaluation

 

BI Reporting discovery analysis

SAC112

Student Systems BI Suite would be deprecated as part of IS strategy  to move away from BI in 2028- 1st step is to establish a strategy doc and plan a roadmap how EUCLID reporting will be managed in 2028 (for review by Information Technology Committee ITC group). The scope will cover functional areas such as:

  • BI reporting, both operational and strategic for use by GaSP, Boards of Examiners ...
  • Technology used (eg csv files, EUGEX materialised views vs APIs/WSO2)
  • Interfaces
  • School downloads

 End of life and legacy work

1-ColdFusion end of life 2028:

  • (1)Personal Tutors PT system will then need to be replaced in 2027. Assess the dependency with the new student case management, 1st implementation completed for Wellbeing/ResLife functionalities, with plan to roll out to schools and Meeting and Notes moving to CMS afterwards. Also the Student Advisors functionality which is using previous PT one will need to be rewritten.
  • (2) EERS will need to be rewritten in 2027: at the moment current processes do not need to be changed, planning a technical upgrade, to be reviewed with Academic Services closed to that date
  • (3) Not required - MyEd Student channels: decision required whether to keep them, user research required by MyEd team (1)My Courses – displays student course details and course results, (2)Programme Of Study – displays details of the students Programme of study.

2- There is a Java version used on the SITS integrator  has reached end of support years ago and needs to be upgraded/rewritten, with significant regression testing (medium sized project ~50d to 100d)- Impact of not doing it: (1) risk if it breaks, (2) security- Previous decision to wait for IDM replacement project (status at business case summer 25 then implementation 2-3 years)

3- As per risk reported EUGEX refresh take longer impacting users SSP resources are required to review and possibly rewrite the EUGEX refresh jobs. Impact not doing it:  a) inefficiency: impact for users during peak period like Boards. Likely that recalculation will be done in spreadsheets on the day to inform decision at Boards, and then keyed in manually in SITS at a later date, 2) increased support, calls from users

 

Section Four: Closed or Withdrawn SSP Projects

Project  Closure report link
SAC100 Data Futures - Embed the HESA Return

https://secure.projects.ed.ac.uk/project/sac100/closure-report

Closed Feb 25

SAC091 Fees Processing Analysis

https://secure.projects.ed.ac.uk/project/sac091/closure-report

Closed Nov 24

SAC103  PATH Upgrade and DRPS Security Enhancement

https://secure.projects.ed.ac.uk/unpublished/project/sac103/closure-report

Closed Aug 24

SAC108 SITS annual double Software Upgrade

https://secure.projects.ed.ac.uk/project/sac108/closure-report

Closed May 25

SAC102 Euclid Technical Legacy - Other

https://www.projects.ed.ac.uk/project/sac102/closure-report

Close Aug 25

 

 

 

   
   
   
   
Programme Status
RAG Status
Overall
AMBER
Has formal escalation taken place?
No

Programme Info

Not available.

Documentation

Not available.