Report for May 2021
- Report Date
- May 2021
Report by Susan Ridder-Patrick (MVMLAT Programme Manager) for Philippa Burrell (MVMLAT Programme Owner) and Catherine Elliot (MVM Portfolio Owner)
Distribution:
-
Vet and Medical School sub-group IT meeting
-
College Administration Team (CAT) meeting
-
College Undergraduate Learning and Teaching (CULT) committee
-
Post Graduate Learning and Teaching (PGLTC) committee
-
Excerpts taken into CSG report
Section One: Programme Commentary, RAG and Resources Update
Commentary
Programme status: The overall status of the MVMLAT programme for May 2021 is GREEN. The Practique Roll-Out project completed this month, following successful use for Vets OSCEs. New risks noted below could affect programme's delivery over the next few months and may cause programme to reutrn to AMBER status.
Risks
- Novel Coronavirus (Covid-19): There is a risk this programme may be impacted by any measures that are implemented to reduce impact from the spread of Covid-19. The risk is held at portfolio level.
There were three new programme risks raised in May:
- Risk 7: MTO may not be sufficently resourced to support a move from Practique to an alternative
- Risk 8: TEL068 delivery timescales/content does not deliver all MVM requirements or cannot deliver in time
- Risk 9: Reduced programme resource in June and July may impact delivery
Project highlights
- MVM125: GREEN - No progress due to delays from the associated sites noted in last month's report
- MVM136: BLUE - Project closed in this month
- MVM139: AMBER - Unable to secure time for final sign-off session
- MVM140: GREEN - Good progress in May with delivery now expected in June
- MVM141: GREEN - Build work underway; scope changed to include work from 21/22 project
- MVM143: GREEN - work completed on multiple locations; further work scheduled and additional requests added into scope
- MVM144: GREEN - Equipment deliveries have taken place and installation planning underway
- MVM145: GREEN - No progress this month
- MVM146: GREEN - Live site being prepared for launch
Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.
Forward Look - May 2021
Section Two: Projects Not Started
Project | Programme Manager's Commentary |
None | No further projects planned for the remainder of 20/21. Projects are being identified for the programme in 21/22 |
Section Three: Projects in Progress
MVM Learning and Teaching Projects Update
MVM125: Connectivity - Off-campus - RAG Status: GREEN Report by Alan GilchristAchievements this period
Issues
Next Steps
|
|
MVM136 Practique Roll-out - RAG Status: BLUE Report by Susan Ridder-PatrickAchievements this period
Issues
Next Steps
|
|
MVM139 Curriculum Mapping Tool (COMMAND) RAG Status: AMBER Report by Arek JuszczykAchievements this period
Issues
Next Steps
|
|
MVM140 CMVM eAssessment RAG Status: GREEN Report by Alistair WallaceAchievements this period
Issues
Next Steps
|
|
MVM141 Replacement for PathCAL/EROS and Labyrinth RAG Status: GREEN Report by Susan Ridder-PatrickAchievements in this period
Issues
Next Steps
|
|
MVM143 Upgrading of Teaching Spaces 2020/21 RAG Status: GREEN Report by Alan GilchristAchievements this period
Issues
Next Steps
|
|
MVM144 Upgrading of student computer labs, teaching and meeting room PCs 2020/21 RAG Status: GREEN Report by Alan GilchristAchievements this period
Issues
Next Steps
|
|
MVM145 Accessibility for MVMLAT applications RAG Status: GREEN Report by Karen HowieAchievements this period
Issues
Next Steps
|
|
MVM146 MBChB Supported Student Database RAG Status: GREEN Report by Richard LawsonAchievements this period
Issues
Next Steps
|
Projects outwith the MVM Portfolio Update
Report by Alan Gilchrist and Karen Howie (LTW):
EEMeC and EEVeC The programme has been and continues to complete projects to close down functionality on both EEMeC and EEVeC with a view to eventually decommissioning. There is a requirement to maintain (read only) access for a period and the programme is in the process of determining those dates for its 3 year plan.
|
|
TEL056: Edinburgh Surgery Online Learn go-live - RAG Status: CLOSED
|
|
DTP001: Apps to User Devices - RAG Status: CLOSED
|
|
HSS022: CAHSS WAM Deployment - RAG Status: BLUE - Closed
|
|
TEL057: Learn Foundations - RAG Status: AMBER Achievements in the last period
Issues
Next Steps
|
|
TEL068: e-Assessment Procurement and Implementation - RAG Status: AMBER Last month.
Issues
Next steps
|
|
TEL071: Provisioning of Teams for Teaching - RAG Status: BLUE An interim options appraisal report updated on the 19th of Jan can be found here. https://www.projects.ed.ac.uk/project/p0345 This project has completed with the delivery of the MS Teams Options Appraisal in May 2021.
|
|
TEL072: Zoom integration for Teaching - RAG Status: BLUE An interim options appraisal report can be found here. https://www.projects.ed.ac.uk/project/p0345 This project has completed with the delivery of the MS Teams Options Appraisal in May 2021 |
Section Four: Closed or Withdrawn Projects
Only those projects closed from 28th June 2019 onwards are included in this table. A full history of completed projects is available on the programme's website.
Project Info | Project Manager's Commentary |
---|---|
MVM126 Upgrading of student computer labs, teaching and meeting room PCs 2018/19 | This project started in October 2018 and closed on 28 June 2019. The Closure report is now available. |
MVM129 Support for OSCEs in Practique for MBChB | This project started in June 2018 and closed on 28 June 2019. The Closure Report is now available. |
MVM131: Migration of 12 applications developed in Biomedical Sciences to central support - Analysis & Strategy | This project started in December 2018 and closed on 28 June 2019. The Closure Report is available to view. |
MVM133: CMVM Curriculum Mapping Tool - Requirements | This project started in April 2019 and closed on 9th August 2019. The Closure Report is available to view. |
MVM130: Upgrading of teaching spaces 2018/19 | This project started in October 2018 and closed on 1st November 2019. The Closure Report is available to view. |
MVM134 MBChB Evaluation System | This project started in September 2019 and closed on 8th April 2020. The Closure Report is available to view. |
MVM137 Upgrading of Student Computer Labs , Teaching and Meeting Room PC 19/20 | This project started in December 2019 and closed on 6th July 2020. The Closure report is available to view. |
MVM132 MBChB ranking reports in BI Suite | This project started in April 2019 and closed on 31 July 2020. The Closure report is available to view. |
MVM138 Vets EMS Placement Management | This project started in January 2020 and closed on 29 September 2020. The Closure Report is available to view. |
MVM112 Technology to support simulation teaching | This project started in September 2017 and closed on 30 September 2020. The Closure Report is available to view. |
MVM135 Upgrading of Teaching Spaces 2019/20 | This project started in December 2019 and closed on 30 September 2020. The Closure Report is available to view. |
MVM516 BMS - Honours Project Portal Future Support | This project started in May 2019 and closed on 19 October 2020. The Closure Report is available to view. |
MVM142 CMVM Study Spaces | This project started in October 2020 and closed on 3 May 2021. The Closure Report is available to view. |
MVM136 Practique Roll-Out | This project started in September 2019 and closed on 21 May 2021. The Closure Report is available to view. |
Section Five: Programme Meeting Minutes
Minutes for all programme meetings are available on the MVMLAT website. Only the most recent five meetings' direct links are included in this table:
Date | Comments |
13 May 2021 | Programme Review Monthly Meeting - April 2021 |
22 April 2021 | Programme Review Monthly Meeting - March 2021 |
8 March 2021 | Programme Review Monthly Meeting - February 2021 |
18 February 2021 | Programme Review Monthly Meeting - January 2021 |
14 January 2021 | Programme Review Monthly Meeting - December 2020 |
Section Six: MVM Portfolio Projects Update
The MVM Portfolio contains three programmes: CMVM Learning and Teaching - MVMLAT (this programme); CMVM Business Administration - MVMBUS and CMVM Research - MVMRES. Information on current work in MVMBUS and MVMRES are available on the following websites: