Report for March 2018

Report Date
March 2018

Define Integrated Identities Requirements

Don MacIver

Achievements in Last Period

  • Overview and project documentation drafted, comments being progressed
  • Engagement with stakeholders and participants
  • Sizing discussions at a high level
  • Communications plan and strategy in review
  • Initiation submitted to WIS
  • Initial communications underway
  • Issues
    • None

Next Steps 

  • Agree brief and planning for submission to WIS.
  • Firm up planning assumptions, stakeholders and estimations
  • Commence requirements gathering. 
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
130.0 days
Activity this month
5.0 days
Activity this year
10.0 days
Activity to date
10.0 days
Estimate to complete current year
120.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Define Integrated Identities Requirements
Code
DTI039
Programme
Digital Transformation - Integrated Identities (DTIP09)
Management Office
ISG PMO
Project Manager
Hilary Shand
Project Sponsor
Dave Berry
Current Stage
Close
Status
Closed
Start Date
01-Feb-2018
Planning Date
25-Aug-2018
Delivery Date
07-Sep-2018
Close Date
28-Sep-2018
Overall Priority
Normal
Category
Discretionary