Report for March 2018
- Report Date
- March 2018
Define Integrated Identities Requirements
Don MacIver
Achievements in Last Period
- Overview and project documentation drafted, comments being progressed
- Engagement with stakeholders and participants
- Sizing discussions at a high level
- Communications plan and strategy in review
- Initiation submitted to WIS
- Initial communications underway
- Issues
- None
Next Steps
- Agree brief and planning for submission to WIS.
- Firm up planning assumptions, stakeholders and estimations
- Commence requirements gathering.
- Approved budget
- 130.0 days
- Activity this month
- 5.0 days
- Activity this year
- 10.0 days
- Activity to date
- 10.0 days
- Estimate to complete current year
- 120.0 days
- Estimate to complete future years
- 0.0 days