Report for April 2018
- Report Date
- April 2018
Define Integrated Identities Requirements
Don MacIver
Achievements in Last Period
- Plan and brief agreed at WIS;
- Engagement with stakeholders and participants;
- Sizing dashboard produced for planning allowing focus for communications and effort;
- Communications plan in progress;
- Presentation to IDM user group;
- BA and SME engaged;
- Initial communications underway
- Issues
- None
Next Steps
- Communicate with IDM UG to provide indication of issues for users;
- Communicate with user groups identified to confirm volume and impact of issues identified;
- Produce documentation, agree format and structure of deliverable;
- Complete requirements gathering.
- Approved budget
- 130.0 days
- Activity this month
- 10.0 days
- Activity this year
- 20.0 days
- Activity to date
- 20.0 days
- Estimate to complete current year
- 110.0 days
- Estimate to complete future years
- 0.0 days