Report for June 2018
- Report Date
- June 2018
|
DTI039 - Define Integrated Identities Requirements
Amber
|
- Approved budget
- 130.0 days
- Activity this month
- 22.0 days
- Activity this year
- 42.0 days
- Activity to date
- 42.0 days
- Estimate to complete current year
- 10.0 days
- Estimate to complete future years
- 0.0 days