This project will deliver timesheet functionality required by both HTBN staff and Research staff involved in Framework 7 (FP7) and Research Council funded projects.
This will be delivered through a phased approach:
Analysis (complete):
Undertake analysis and design to agree data model for both user groups along with the individual reporting, approval workflow and user interface requirements for each user group.
Phase 1 (complete):
Provide functionality to allow both user groups to generate, store and electronically submit timesheets for approval.
Phase 2 (complete):
Enhance the functionality provided at Phase 1 to further develop the workflows/approval process, reporting and verification.
All project documentation up to 6th August 2012 can be found at: http://www.old.projects.ed.ac.uk/areas/finance/general/FIN072/index_table.shtml
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
December 2012 | BLUE | 628.0 days | 619.0 days | 0.0 |