Project journal

Title Description Author Post date
Meeting with business lead

The project team met with the business lead on 21-8-14 to discuss project progress and agree next steps.

Morna Findlay 21-Aug-2014
Weekly update w/c 04/08/14
  • Planning & estimation meeting held with stakeholders from IS Apps and Finance
  • New project estimate produced - an additional 29 days are required to complete the project.  Link to new estimate
  • New project plan produced - estimated completion date is now 24th Sept.
Dawn Holmes 08-Aug-2014
Purging and Archiving for eFinancials

 

This project will enable Finance to safely and securely delete obsolete data from eFinancials as a routine support task. The project will make use of standard ABS purging routines to remove obsolete data but will enlist the assistance of IS Applications in archiving purged data for a period of two years allowing  confidence in the purging routines to be gained.

 

 

More information can be found about this project at: https://www.projects.ed.ac.uk/project/fin097

Morna Findlay 09-Jun-2014

Project Info

Project
Purging and Archiving for eFinancials
Code
FIN097
Programme
Finance (FIN)
Project Manager
Morna Findlay
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
08-Apr-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
20-Oct-2014