- Planning & estimation meeting held with stakeholders from IS Apps and Finance
- New project estimate produced - an additional 29 days are required to complete the project. Link to new estimate
- New project plan produced - estimated completion date is now 24th Sept. Link to new project plan
- Issue log entries created but not yet submitted to WIS for approval as Project Sponsor has not yet agreed these changes due to annual leave
- Jiras raised to track the remaining tasks
- Asta bookings raised to request resource to complete the project