Report for April 2015
- Report Date
- April 2015
Achievements this period
- Applications Management have been working with FIS to try and resolve the issues with the eFinancials interface
Issues
- The pilot was not launched as planned this month due to issues uncovered with the eFinancials upload routine. These issues were not detected during UAT and are preventing any expense claims from being uploaded for payment. The issues are being worked on by Appications Management and although some progress has been made, we stil have not been able to successfully load any expense claims. This additional work is causing the budget to escalate and the pilot cannot launch until this is resolved, therefore the project has been placed on RED status as we are currently unable to deliver the project. We may now need to involve ABS to try and find an acceptable resolution.
Next steps
- Resolve issues with eFinancials upload routine
- Close the project
Target date | Title |
---|---|
06-Apr-2015 | Pilot launch |
20-Apr-2015 | Closure |
- Approved budget
- 444.0 days
- Activity this month
- 5.2 days
- Activity this year
- 302.0 days
- Activity to date
- 459.1 days
- Estimate to complete current year
- 3.1 days
- Estimate to complete future years
- 0.0 days