Report for May 2015

Report Date
May 2015

 

Achievements this period

  • Latest version of application and updated interfaces were deployed to Live
  • First live claim was successfully passed to eFinancials and paid

Issues

  • Pilot still has not been launched.  This is preventing the project from closing and so is continuing to utilise time and resource.

Next steps

  • Agree pilot launch date with Finance

 

Project Status
RAG Status
Overall
AMBER
Change Status
Activity
Approved budget
444.0 days
Activity this month
1.8 days
Activity this year
299.7 days
Activity to date
455.8 days
Estimate to complete current year
2.4 days
Estimate to complete future years
0.0 days