Report for May 2015
- Report Date
- May 2015
Achievements this period
- Latest version of application and updated interfaces were deployed to Live
- First live claim was successfully passed to eFinancials and paid
Issues
- Pilot still has not been launched. This is preventing the project from closing and so is continuing to utilise time and resource.
Next steps
- Agree pilot launch date with Finance
- Approved budget
- 444.0 days
- Activity this month
- 1.8 days
- Activity this year
- 299.7 days
- Activity to date
- 455.8 days
- Estimate to complete current year
- 2.4 days
- Estimate to complete future years
- 0.0 days