Organisation

Work/Task Breakdown

Business Analysis - Data Source and Dashboard configuration, users and permissions identification. 

Gateway and Systems Design and analysis and specification.

Development Environment build.

Gateway software build and configuration.

Integration and integration testing.

User Acceptance Testing.

SLA & OLA and operational documentation production.

Deployment - Build and deploy to live environment.

Project Closure

Resources, Skills and Costs

Project Services Project Manager 19 Days
Business Analysis , User Acceptance Testing, Data Source and User Identification Dev Tech 5 Days
Systems Analysis Design Dev Tech 5 Days
Build Test Environment Dev Tech 7 Days
Acceptance Service Management / Production Managemet 5 Days
Deployment Production Managemet 5 Days

 

Project Governance

This project will follow the standard project governance in Project Services. Any changes to major milestones (Initiation, Planning, Delivery, Closure) will be approved by the Project Sponsor, Project Team and WIS. Major milestones achievements and changes will be submitted to WIS for approval/noting as necessary.

 

Project Stakeholders

Name Business Area Role  
Alastair Duthie CAHSS Academic Policy Officer  
Ana Hyn Application Services Production Management  
Andrew Thomson CAHSS Business Lead  
Fraser Muir CAHSS Senior Business Partner  
Geoff Cropley ISG Applications Project Manager

Project Team

Gillian Henderson                                                     ISG Development Services                                                          Senior Database & Systems Manager                
Katy McLeod CAHSS Business Intelligence Analyst  
Mark Dobbing ISG Development Services Systems Administrator  
Mark Lang Dev Tech Manager Dev Tech  
Mark Ritchie ISG Applications Head of Project Services  
Muriel Mewissen ISG Applications Programme Manager  
Nick Tordoff ISG Applications Programme Manager BI/MI  
Peter Jackson ISG Dev Tech Application Development

Project Team

Stefan Kaempf Production Services Head of Production Management  
Suran Perera Application Services Production Management

Project Team

Susan Cooke ISG Service Management Service Management

Project Team

Alex Carter Sponsor ISG Service Management  

 

 

Project Estimations

HSS019 3Point Estimate

 

 

 

Project Info

Project
Power BI Gateway Service
Code
HSS019
Programme
Z.Digital Transformation - BI Tools (DTIP08) - CLOSED
Management Office
ISG PMO
Project Manager
Geoff Cropley
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
18-Sep-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
18-May-2018
Overall Priority
Normal
Category
Discretionary

Documentation

Plan