Overview

Hope Park Counselling Centre  offers counselling to individuals aged sixteen and over living in the Edinburgh area.  It is the University's in-house counselling centre for the full time MCID (Masters in Counselling: Interpersonal Dialogue) students and the Professional Doctorate students in Psychotherapy and Counselling.  Hope Park is also a training and research centre that serves the local community.  The centre currently uses an MS Access database to manage its core processes, but the database solution is no longer capable of being supported or developed and therefore requires replacement.  Early market engagement in a previous project (coded HSS018) found several feasible software options available on the market to replace the database, and recommended a procurement and implementation.  This project will carry out the procurement only.

In Scope

  • Procurement strategy
  • Pre Qualification Questionnaire
  • Specification of requirements
  • Invitation to Tender
  • Evaluation and selection of supplier / product
  • Awarding of contract to selected supplier (an initial four year contract)

Out of scope

  • Implementation (this will be a separate project to follow the procurement)

Objectives and Deliverables

Objectives and Deliverables

Priority

Owner

O1 To set out a procurement strategy

 

 

D1. Procurement Strategy document

Must Have

Procurement Office

IS Applications

Hope Park

O2 To formally specify requirements for replacing the database

 

 

D2. A Pre Qualification Questionnaire Must Have

Procurement Office

IS Applications

Hope Park

D3. A requirements document specifying mandatory and non-mandatory requirements

Must Have

Hope Park

IS Applications

O3 To invite bids from prospective suppliers and request quotes

 

 

D4. An advertisement / Invitation to Tender

Must Have

Procurement Office

IS Applications

Hope Park

O4 To evaluate and select a supplier and product

 

 

D5. Evaluation criteria, evaluation sessions with suppliers, selection review with evaluation panel

Must Have

Procurement Office

IS Applications

Hope Park

D6. Privacy Impact Assessment (for GDPR) and Equality Impact Assessment (for accessibility) Must Have

CAHSS

Disability Office

O5 To contract with the selected supplier    
D7. A signed contract with the supplier, with payment Must Have CAHSS

Benefits

Below is a list of benefits related to implementing a new system relying on a successful procurement.

  • A supported client management application
  • An application compliant with General Data Protection Regulation (GDPR)
  • Improved backup of data using a cloud based solution
  • Reduction in use of paper based processes and records, and enhanced reporting tools
  • Ability to access application and data from multiple locations, including remote access
  • Single system for managing documents including client correspondence, with system based audit trail
  • Potential to integrate enquiry management with Hope Park website to facilitate 24/7 enquiries
  • A system that can grow and be flexible with the demands that may be placed on it as Hope Park evolves
  • A less onerous training requirement
  • A user friendly system

Success Criteria

  • A sufficient number of feasible bids received
  • A clear winner arising from the evaluation and selection process
  • A solution that meets all the mandatory business requirements
  • Contract signed and first year payment sent to selected supplier before end of financial year (by 31/07/18)

Project Milestones

Target Date

Title
30-Mar-2018 Planning
13-Apr-2018 Procurement Strategy signed off
27-Apr-2018 Requirements Specification completed
04-May-2018 PQQ and ITT issued
25-May-2018 Supplier Response Deadline
22-Jun-2018 Evaluation complete
06-Jul-2018 Delivery (Award Contract) and Payment made
20-Jul-2018

Closure

Project Info

Project
Hope Park Counselling Centre System Procurement
Code
HSS021
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Ben Armstrong
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Start Date
19-Feb-2018
Planning Date
n/a
Delivery Date
n/a
Close Date
03-Aug-2018
Overall Priority
Normal