Report for March 2019

Report Date
March 2019

Achievements this period

  • All project deliverables are complete
  • There has been a delay in sponsors approving closure report and a change has been raised to move the closure milestone

Issues

None

Next Steps

  • Sponsor approval for project closure
  • Project closure

 

Project Milestones

Target Date Previous Date Title Stage Complete
20-Jul-2018 No date available                End of Planning Initiate Yes
28-Sep-2018          No date available Design Standards, Use Cases and Content Types Definition Complete Execute                Yes
22-Oct-2018 No date available Digital Notice Boards & Signage Guidelines Complete Execute Yes
08-Nov-2018 No date available Target Operating Model Definition Complete Execute Yes
23-Nov-2018 No date available Digital Display Service Definition Complete Execute Yes
14-Dec-2018 No date available Complete Design Templates Execute Yes
31-Jan-2019 No date available Technology Options Paper Complete Execute No
12-Apr-2019 14-Feb-2019 Closure Close No

 

 

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Time
Within Tolerance
Cost
Within Tolerance
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
No
Change Commentary
Closure moved from 14 Feb to 12 Apr to allow Business stakeholder to review and sign off.
Activity
Approved budget
30.0 days
Activity this month
0.0 days
Activity this year
30.0 days
Activity to date
33.5 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
First Impressions - Digital Signage
Code
HSS025
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Geoff Cropley
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
15-Jun-2018
Planning Date
20-Jul-2018
Delivery Date
31-Jan-2019
Close Date
19-Apr-2019
Overall Priority
Normal
Category
Discretionary