w/c 23rd March 2020

  • Go-Live preparations
    • Data from the live MS Access database has been extracted, and transferred to the supplier on 24/03/20
  • SSO
    • Call raised to update DNSĀ 

Project Info

Project
Hope Park Counselling Centre System Implementation
Code
HSS027
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
24-Aug-2018
Planning Date
29-Aug-2018
Delivery Date
27-May-2020
Close Date
06-Nov-2020
Overall Priority
Normal
Category
Discretionary