w/c 20th January 2020

  • Go-Live Preparations
    • GoCab paperwork submitted for go-live on 5th February
    • Request to Applications Management to commence Deployment CheckList 
    • Request for Technology Management  resource to complete Deployment CheckList 
  • piccl submitted to WIS re revised dates and budget 
  • User Acceptance Testing 
    • UAT Status schedule prepared 
    • UAT commencing 
    • Review of outstanding JIRAs undertaken with the business and the suppler
  • Risk Log updated
  • SSO
    • Certificate for live environment received and forwarded onto Dev Tech
  • Secure database access requirements forwarded onto Hope Park
  • Conference call notes, whilst reviewing outstanding JIRAs
    • Issues

      • Bugs would have to be resolved prior to the go-live
      • Requirements associated with field changes, moving fields, renaming labels, assigning default values to drop downs would be recognised as being in scope and would be applied if time available
      • Additional requirements and new reports would be deemed out of scope of the project and would require to be actioned under future support arrangements
  • SalesAgility

    • Technical Lead has returned to assist with any technical issues
    • An additional developer has been assigned to the project
  • Next Review

    • Scheduled for Wednesday 29th January, 3.00 p.m. – Supplier to organise a GoTo meeting

Project Info

Project
Hope Park Counselling Centre System Implementation
Code
HSS027
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
24-Aug-2018
Planning Date
29-Aug-2018
Delivery Date
27-May-2020
Close Date
06-Nov-2020
Overall Priority
Normal
Category
Discretionary