Hope Park Counselling Centre System Implementation
Hope Park Counselling Centre System Implementation
Home
Projects
Hope Park Counselling Centre System Implementation
Journal
w/c 10th February 2020
w/c 10th February 2020
This article was published on
Mar 23, 2020
Project Info
Project
Hope Park Counselling Centre System Implementation
Code
HSS027
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
24-Aug-2018
Planning Date
29-Aug-2018
Delivery Date
27-May-2020
Close Date
06-Nov-2020
Overall Priority
Normal
Category
Discretionary
More project information
Documentation
Initiate
Initiation Documents
Plan
Project Brief
Execute
No documents
Deliver
No documents
Close
Closure Report