Overview

Background

Digital Collections Migration – LUNA (LUC074) builds on a number of projects from the DLIB Programme (specifically DLIB005, DLIB008, and DLIB020), which established that a new digital collections platform was required to improve management of and access to Library & University Collections’ digital heritage assets

An open-source solution, Archipelago, was procured in 2022 but design and migration were paused due to lack of staff resource. With the recruitment of a Digital Collections Support Officer and more resource in the Systems & Development team, this work is now ready to commence. 

This project is closely linked to and will run in tandem with LUC073 Digital Collections Platform Implementation.

Scope

This project is concerned with the migration of all digital collections material from LUNA to Archipelago.

The migration covers all collections material on LUNA, regardless of whether it is public / private or managed / non-managed by Digitisation & Making Services (D&MS), and will be undertaken in several phases based on these criteria. 

Out of scope

The migration of any digitised / digital heritage collections on any platforms other than LUNA (e.g., PDFs on OpenBooks, AV collections from the School of Scottish Studies, 3D objects, collections held on lac store only).

Non-collections images such as staff portraits and documentary photography are also out of scope. Migration of this material will form the basis of future projects. 

The project is not concerned with the relationship between Archipelago and Collections.Ed, and will not cover longer term digital preservation of the assets. These will also form the basis of future projects. 

Objectives and Deliverables

Ref

Description 

Priority 

(MoSCoW) 

Owner 

O1 

 To establish appropriate workflows and approaches for migration

 

 

O1D1  Assessment of public and private D&MS-managed LUNA collections MUST  Gabi Migdalska (PROJECT TEAM)

O1D2

Report outlining number of items in each of the four main categories: items gone through Goobi; item-level catalogued; collection-level catalogued; no information

 

MUST 

 

Gabi Migdalska (PROJECT TEAM)

O2

 Migrate all existing LUNA collections to the new collections platform

 

 

O2D1

Migration of D&MS-managed Goobi material 

 

MUST 

 

Scott Renton (PROJECT TEAM)

O2D2

Migration of D&MS-managed item-level non-Goobi material

 

MUST 

 

Scott Renton (PROJECT TEAM)

O2D3 Migration of D&MS-managed non-item-level non-Goobi material MUST  Scott Renton (PROJECT TEAM)
O2D4 Migration of non-D&MS-managed material MUST  Scott Renton (PROJECT TEAM)
O2D5 Migration of material added to LUNA since 31/12/2023 MUST  Scott Renton (PROJECT TEAM)
O2D6 Migration of session papers MUST  Scott Renton (PROJECT TEAM)

 

O3  

 

Agree system for ongoing uploads to Archipelago post migration

 

 

O3D1

 Build and distribute workflow for ongoing uploads to Archipelago post migration

MUST 

Scott Renton (PROJECT TEAM)

Benefits

Benefit

Recipient(s)

Timeline for Realisation

Owner

Collections moved to a system which is better designed to meet the needs of users Heritage Collections staff  Project end

Rebecca Hirsch

Process of migration involves systematic review of existing digital collections for the first time, allowing for issues to be resolved   Digital Library team  Project end

Rebecca Hirsch

Remediation of technical debt (collections material that is no longer required) Digital Library team  Project end

Rebecca Hirsch

Gain clarity on management and use of collections / images for the longer term and standardisation of asset management  Heritage Collections staff  Project end Rebecca Hirsch

Success Criteria

  • Digital assets migrated successfully 

  • Data associated with digital assets migrated successfully 

  • Workflow agreed for ongoing uploads of new material to collections platform 

  • Agreed approach in place for longer term management and use of digital collections 

Project Milestones

 

Stage Milestone Due Date Previous Date
Initiate Project Initiation (MAJOR MILESTONE) 31-May-2024 No date available
Plan LUC073 complete and closed 31-Jan-2025 No date available
Plan Project Brief Completion (MAJOR MILESTONE) 28-Feb-2025 No date available
Build Process for migration of Managed Goobi Material agreed and signed off 28-Mar-2025 No date available
Build Sample of Managed Goobi Material migrated into TEST environment 11-Apr-2025 No date available
Accept Sample of Managed Goobi Material signed off in TEST environment 18-Apr-2025 No date available
Deliver Migration of Managed Goobi Material into LIVE environment complete 30-Apr-2025 No date available
Accept Managed Goobi Material post-migration checks complete and signed off 16-May-2025 No date available
Deliver Soft launch of Archipelago platform in LIVE environment 29-Aug-2025 No date available
Accept Post-soft launch of Archipelago platform checks complete and signed off 12-Sep-2025 No date available
Build Process for migration of Managed Public Non-Goobi Material agreed and signed off 05-Dec-2025 No date available
Build Sample of Managed Public Non-Goobi Material migrated into TEST environment 09-Jan-2026 No date available
Accept Sample of Managed Public Non-Goobi Material signed off in TEST environment 23-Jan-2026 No date available
Deliver Migration of Managed Public Non-Goobi Material into LIVE environment complete 30-Jan-2026 No date available
Accept Managed Public Non-Goobi Material post-migration checks complete and signed off 13-Feb-2026 No date available
Build Process for migration of Managed Private Non-Goobi Material agreed and signed off 12-Jun-2026 No date available
Build Sample of Managed Private Non-Goobi Material migrated into TEST environment 03-Jul-2026 No date available
Build Process for migration of Session Papers agreed and signed off 10-Jul-2026 No date available
Accept Sample of Managed Private Non-Goobi Material signed off in TEST environment 17-Jul-2026 No date available
Build Session Papers migrated into TEST environment 24-Jul-2026 No date available
Deliver Migration of Managed Private Non-Goobi Material into LIVE environment complete 31-Jul-2026 No date available
Accept Managed Private Non-Goobi Material post-migration checks complete and signed off 07-Aug-2026 No date available
Accept Session Papers signed off in TEST environment 07-Aug-2026 No date available
Deliver Session Papers migrated into LIVE environment 14-Aug-2026 No date available
Accept Session Papers post-migration checks complete and signed off 21-Aug-2026 No date available
Deliver Full launch of Archipelago in LIVE environment (MAJOR MILESTONE) 28-Aug-2026 No date available
Accept Post-hard launch of Archipelago platform checks complete and signed off 11-Sep-2026 No date available
Deliver Final switch off of LUNA 18-Sep-2026 No date available
Close Project Closure (MAJOR MILESTONE) 30-Sep-2026 No date available

Project Info

Project
Digital Collections Migration: LUNA
Code
LUC074
Programme
Library & Collections - Digital Library BAU (LUCDL)
Management Office
ISG PMO
Project Manager
Jack Ross
Project Sponsor
Rebecca Hirsch
Current Stage
Execute
Status
In Progress
Start Date
19-Jan-2024
Planning Date
05-Mar-2025
Delivery Date
28-Aug-2026
Close Date
30-Sep-2026
Overall Priority
Normal

Documentation